Container Straddle Carrier
Container straddle carriers are used for stacking and moving containers. These straddle carriers have the ability to stack containers up to 4 layers. The normal capacity of Weihua straddle carriers is 35t.
Read More >
Container straddle carriers are used for stacking and moving containers. These straddle carriers have the ability to stack containers up to 4 layers. The normal capacity of Weihua straddle carriers is 35t.
Read More >
This railway container gantry crane is for the railway container logistics transport. The spreader is a 360° rotating spreader.
Read More >
This container spreader is a dedicated lifting tool of container cranes for bulk material container lifting, transport and discharging. It is a fully hydraulically driven container spreader equipped with tipping mechanism, telescopic mechanism, door opening and closing mechanism, etc.
Read More >
Some equipment need to be prepared before crane erection. The erection steps and details of Weihua Double Girder Gantry Crane: Confirm position, legs erection, main girder erection, trolley hoist installation, etc.
Equipment need to be prepared before crane erection: Wrench tool box, gear oil, welder, hydraulic jack, chain block, steel tape measure, tow rope, traction wire rope, wire rope sling, support equipment for leg installation, installation platform for leg installation, forklift, truck crane, etc.

The erection steps and details of Weihua Double Girder Gantry Crane:
Fill the gearbox oil – confirm installation position - confirm the diagonals are equal – main beam girder connection installation – end carriage installation – drag chain installation – guardrail installation – saddle installation – lower beam and wheels installation – legs installation – pull rope and platform installation – cable drum installation – ladder installation – working platform installation – confirm the diagonals are equal – cabin installation – ladder installation – main beam installation with leg support equipment – main beam and legs connection – remove the working platform and pull rope – remove leg support equipment – trolley hoist hoisting and installation – drag chain installation – rain cover installation – wire rope torsion release – connect wire rope with sling – sling pull the wire rope to drum and winding – lower the wire rope to ground – hook installation.
There is a erection guide video for your reference.